project description: ELEKTRISOLA SDN. BHD.

PHASE 2

EM has a current workforce of 800 employees who are mostly local people from Janda Baik and the vicinity of Pahang. Project Elektrisola Phase 2 was developed between August to November 2019 The total installed capacity of phase 1 and 2  is 4.5 MWp.

Elektrisola (Malaysia) Sdn. Bhd.

Project Key Data Phase 2

Project Development/EPC: Coara Solar Sdn. Bhd.

Project Owner: Elektrisola (Malaysia) Sdn. Bhd.

Location: Janda Baik, Pahang

Installed Capacity: 3.6MWp

Development: August – November 2019

Design, Procurement, Construction: December 2019 – July 2020

Commissioning Date: Commissioned in July 2020

Solar Production: ~4,800,000 KWh/year

Performance ratio: 83-84% among the highest in the country due to its location on higher ground in Janda Baik