project description: ELEKTRISOLA SDN. BHD.
PHASE 2
EM has a current workforce of 800 employees who are mostly local people from Janda Baik and the vicinity of Pahang. Project Elektrisola Phase 2 was developed between August to November 2019 The total installed capacity of phase 1 and 2 is 4.5 MWp.
Elektrisola (Malaysia) Sdn. Bhd.
Project Key Data Phase 2
Project Development/EPC: Coara Solar Sdn. Bhd.
Project Owner: Elektrisola (Malaysia) Sdn. Bhd.
Location: Janda Baik, Pahang
Installed Capacity: 3.6MWp
Development: August – November 2019
Design, Procurement, Construction: December 2019 – July 2020
Commissioning Date: Commissioned in July 2020
Solar Production: ~4,800,000 KWh/year
Performance ratio: 83-84% among the highest in the country due to its location on higher ground in Janda Baik